50 percent planned, 120 percent tied up in day-to-day operations
On paper: 50 percent allocated to the project. In practice: 120 percent tied up in day-to-day operations.
I've seen this happen in almost every transformation programme I've worked on. On paper, everything looked good: a clear roadmap, defined milestones, and identified resources. And yet, the project still didn't move forward.
Not because the team didn't want to. Not because the concept was wrong. But because the very people who were assigned to the project were also fully responsible for their respective lines of business.
What happens next
Meetings get postponed. Results come later. Decisions remain pending. The resources exist on paper, but not in everyday life.
The problem isn't a lack of commitment. It's a lack of priorities. If no one actively decides what takes priority, something very predictable happens: day-to-day business takes over.
Transformation doesn't require more resources. It requires real decisions about what comes first.
What You Can Do Tomorrow
Ask the key people on your project which day-to-day tasks they can delegate or postpone over the next four weeks. If they can’t answer that, the 50 percent target is just a number.
Read more about this in the newsletter.
A detailed analysis of this topic, including background information and the approach taken, can be found at The CFO Lens. Every Tuesday, free of charge, and you can cancel at any time.
What's on your agenda?
In 30 minutes, I'll work with you to figure out where the problem lies and what you need right now. You'll walk away from the conversation with an initial assessment, even if we don't end up working together.

