Status green, even though it's stuck
Status green is always an assessment. But not always a calculated one.
Sometimes that's what happens when there's nothing to calculate.
A work package contains more tasks than anyone in the room can keep track of. There is no total number for them, just a list. A list cannot be reported in the Steering Committee. So someone makes an estimate.
It’s worth taking a closer look at how this estimate is arrived at: twenty minutes before the meeting, without an overview of the individual tasks, and knowing that a “red” status requires forty minutes of explanation while a “green” status requires none. The estimate is: “green” status.
Anyone would make that decision
Every step of this makes sense. A red status has immediate consequences—specifically for the person reporting it. A green status has consequences later on—for everyone. Anyone would make that decision.
The usual response to this is a call for more honest reporting. It won't last past the next meeting, because there has never been a lack of honesty.
If work packages are structured in such a way that no one can report their status without guessing, you’re asking for a number that doesn’t exist—and making decisions based on that.
What was missing was a unit worth reporting on at all.
What You Can Do Tomorrow
Before you ask whether a programme is on track, check to see if its work packages are structured in a way that allows you to measure their progress rather than estimate it. If that’s not the case, any status—whether green, yellow, or red—is just a guess.
Read more about this in the newsletter.
A detailed analysis of this topic, including background information and the approach taken, can be found at The CFO Lens. Every Tuesday, free of charge, and you can cancel at any time.
What's on your agenda?
In 30 minutes, I'll work with you to figure out where the problem lies and what you need right now. You'll walk away from the conversation with an initial assessment, even if we don't end up working together.